DETAILED ENGINEERING DESIGN OFFSHORE FLOWLINE INFILL WELLS
PROJECT AT TANGGUH LNG FACILITIES
• Construct flowline to connect each Xmas tree wing valve to existing VRA production manifold with single flowline
• configuration for each well (no comingle).
• Complete each flowline with its accessories such as wet gas flow meters, choke valve, non intrusive sand detector, sampling point, and through conduit double expanding gate valve (10” bel valve).
• Connect the wells to VRA WHCP system.